  • 21 A claim of lien filed under this Act takes effect from the time work began or the time the first material was supplied for which the lien is claimed, and it has priority over all judgments, executions, attachments and receiving orders recovered, issued or made after that date.

1997-45-21, effective February 1, 1998 (B.C. Reg. 1/98).